The Town has contracted with Aggregate Industries to repave the following streets or portions thereof: Argilla Rd (County Rd to Rocky Hill Rd), Rocky Hill Road, Old England Road, Spillers Lane, Randall Road and Charlotte Rd. Aggregate Industries will begin raising castings on Tuesday September 3rd and anticipates two days for that work. They will also have crews will be in town installing the berm as needed as well as addressing driveway aprons. Top Course paving is scheduled for the week of September 15th and is anticipated to take two day to complete. This project is weather dependent, so any inclement weather will delay the work.