On Monday November 16, 2015 Brox will be raising all of the gate boxes, manholes covers and catch basin grates to the final paving elevation this work will be completed on Tuesday. Final top course paving is scheduled to begin on Wednesday November 18, 2015 and is scheduled to take two days to complete.