The Town has contracted with Brox Industries for the repaving of Brown Sq, Brewery Pl, South Village Green, Old Essex Rd, Northgate Rd from Essex Rd to Old Essex Rd, Linebrook Rd from Pillowlace Ln to Boxford Rd, Boxford Rd from Linebrook Rd to approximately the Hood Pond Landing, and Town Farm Rd from Fowler’s Ln to Greens Point Rd.
PAVING UPDATE
TUESDAY MAY 16TH BROX WILL BEGIN BINDER PAVING AT 7:00 AM ON LINEBROOK ROAD AND MOVE TO BOXFORD RD. WEDNESDAY MAY 17TH BROX WILL BEGIN BINDER PAVING AT 7:00 AM ON BROWN SQUARE AND MOVE TO SOUTH VILLAGE GREEN ONCE COMPLETE. ONCE COMPLETE AT SOUTH VILLAGE GREEN BROX WILL MOVE TO TOWN FARM ROAD TO INSTALL BINDER PAVING IN THE AFTERNOON. MONDAY MAY 22ND BROX WILL BEGIN BINDER PAVING AT 7:00 AM AT NORTHGATE RD AND OLD ESSEX ROAD.
- WED May 17th:
- BUSBY: Hone over Brown Square, South Village and Town Farm.
- BROX: Brown Square (est. 350 Tons)
- BROX: South Village Green (est. 200 Tons)
- BROX: Town Farm Rd (est. 510 Tons)
- THURS May 18th
- FRI May 19th
- No paving in Ipswich
- TANGO: starts adjusting Structures
- MON May 22nd:
- BUSBY: Hone over Northgate and Old Essex for a 7am pave.
- BROX: Northgate (est. 200 Tons)
- BROX: Old Essex (est. 170 tons)
- TANGO: Adjusting Structures
- MCIVER: Sidewalks
MAY 24th WEDNESDAY: Brox
- Brox anticipates having a paving crew returning to begin paving the top course.
THIS SCHEDULE IS SUBJECT TO CHANGE EITHER DUE TO WEATHER OR ANY OTHER UNFORESEEN CONDITIONS.